Skip to content

journal

how to compare interior quotes without losing the scope

Compare interior quotes by scope, quantities, specifications and exclusions. A practical guide to reading contractor prices before work starts in a home.

Plum House dining area with a black marble table on stone columns and a lit teak display wall

The lowest total on an interior quote is not necessarily the lowest cost of completing the same work. One contractor may include protection, hardware and finishing. Another may leave them to be priced later.

Before comparing prices, make the scope comparable. We use the drawings and specifications to define what is being priced. Without that shared basis, you are comparing assumptions.

give everyone the same information

Issue the same drawing set, finish schedule and scope to each contractor. Identify the version and date. If a question changes the scope, share the answer with everyone pricing it.

Include the building's working arrangements, access constraints and any known restrictions. A quotation based on unrestricted access cannot be compared fairly with one that allows for limited working hours.

separate quantity from rate

A total for “wardrobes” conceals several decisions. How many units are included? What are their dimensions? Which board, finish and hardware are specified? Does the price include internal fittings and installation?

Where possible, compare the quantity and rate as well as the final amount. If one quantity is substantially different, resolve that before negotiating the rate.

read exclusions first

Highlight excluded items and unclear allowances. Common questions concern debris removal, temporary protection, final cleaning, transport, scaffolding where relevant, and work needed after another trade finishes.

An allowance is not the same as a selected, priced product. Ask what happens when the actual choice differs from that allowance. Record the decision before the item is ordered.

Plum House dining area with a black marble table on stone columns and a lit teak display wall
A timber display wall, stone coffee tables and brass-toned console in Plum House, Breach Candy.

make a comparison sheet

ItemWhat to record
ScopeThe drawing or specification that defines it
QuantityThe measurement basis and included amount
MaterialProduct, grade, thickness and finish where relevant
HardwareNamed product or clearly defined equivalent
InstallationFixing, finishing and making good
ExclusionsWork priced separately or not included
ProgrammeLead times and the proposed sequence

This sheet should explain differences, not simply rank the totals.

decide how changes will be priced

Ask how additions and omissions will be recorded. A written change should identify the reason, price effect and time effect before the work proceeds.

Keep approvals in one place. A verbal decision on site is easy to remember differently when the final bill arrives.

ask who is responsible for interfaces

The difficult bits often sit between packages: a stone edge against a cabinet, lighting inside joinery or a fitting that needs a separate backing. Check who measures, supplies, installs and makes good each part.

Where responsibility is split, name the person coordinating it. An inexpensive item can become expensive if two trades assume the other will finish it.

choose on completeness as well as price

A useful quotation is specific enough to build from. It shows that the contractor has understood the drawings, asked sensible questions and allowed for the work required.

Price still matters. But negotiate an understood scope, rather than accepting a lower total whose missing parts will emerge later.

read next

Explore our apartment renovation work and the Plum House case study. For a related guide, read interior design cost mumbai.

start a conversation.